Bound for Platforms 6-9 at Perth Railway Station, these large structures are getting their finishing touches in house by our X-men before they are moved into place next month. They'll be located under the roof canopy and display a range of advertising material to entertain passengers whilst they wait for the next train to arrive.
The PTA OSH team came and inspected our movement methodology this week and I'm delighted to say the left without passing comment (always a positive sign!).
Meanwhile, out on site, our night X-men shift workers have been hard at work preparing the site environment for the signage arrival in the next few weeks. To avoid and accommodate the train timetabling, the shift patterns have meant our installers have been working 1am-4am shift patterns so we haven't seen them around much during the day as you can imagine. Can't wait to see these ones lit up.